Material Consumption
Material consumption
Material Consumption functionality allows you to have multiple consumption Stock Entry against a Work Order. To enable this, go to Manufacturing > Manufacturing Settings.
Once enabled, a Material Consumption button will be available in Work Order once started.
When button is clicked, it will do the following:
- It will create Stock Entry with purpose Material Consumption for Manufacture.
- If the "Backflush Raw Materials Based On" in the Manufacturing Settings is set to BOM, if will propose to consume all required qty for manufacture.
- If the "Backflush Raw Materials Based On" in the Manufacturing Settings is set to Material Transferred for Manufacture, if will propose to consume all transferred qty for manufacture.
- Once submitted, it will update Consumed Qty column in the Work Order.
- In succeeding Material Consumption, it will suggest unconsumed qty.
- Once "Finish" button is clicked in Work Order, it will take into account consumed qty.
Validations
- If "Allow Multiple Material Consumption" is not set in Manufacturing Settings but "Material Consumption for Manufacture" is use in Stock Entry.